Traffic Alert: Utility work begins in center of Scarsdale

Con Edison will be replacing a 200-foot length section of steel gas main, including several customer service lines, from 8 a.m. to 4:30 p.m. Monday through Friday along Spencer Place between Boniface Circle and Harwood Court in the village center.

News 12 Staff

Feb 28, 2024, 5:23 PM

Updated 149 days ago

Share:

Today marks the first day of a utility project in Scarsdale.
Con Edison will be replacing a 200-foot length section of steel gas main, including several customer service lines, from 8 a.m. to 4:30 p.m. Monday through Friday along Spencer Place between Boniface Circle and Harwood Court in the village center.
Village officials say some parking will be restricted, and there will also be some partial lane closures.
The project is set to take about three weeks, two for road excavation and utility replacement and then an additional week of restoration.